Permitting Action Modification History

Complete
Section 106 concluded and SHPO concurrence was obtained ahead of schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-01-2025 06-25-2025 --- Yes
Section 106 consultation concluded (Agency Action) 12-15-2025 11-26-2025 --- Yes
In Progress
NTIA sent out the invitation to consult letter for Section 106 of the National Historic Preservation Act for the NANA Regional Broadband Network Project on June 25, 2025, ahead of the current Permitting Dashboard milestone scheduled for August 1, 2025. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-01-2025 06-25-2025 --- Yes
Section 106 consultation concluded (Agency Action) 12-15-2025 12-15-2025 --- No
In Progress
NTIA sent out the invitation to consult letter for Section 106 of the National Historic Preservation Act for the NANA Regional Broadband Network Project on July 25, 2025, ahead of the current Permitting Dashboard milestone scheduled for August 1, 2025. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-01-2025 07-25-2025 --- Yes
Section 106 consultation concluded (Agency Action) 12-15-2025 12-15-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-01-2025 08-01-2025 --- No
Section 106 consultation concluded (Agency Action) 12-15-2025 12-15-2025 --- No