Permitting Action Modification History

Complete
Consultation completed earlier than scheduled.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-15-2025 04-15-2025 --- Yes
NOAA determines ESA Consultation Package is Complete - Informal (Agency Action) 06-13-2025 05-15-2025 --- Yes
ESA Consultation Concludes (Agency Action) 08-13-2025 05-28-2025 --- Yes
In Progress
ESA consultation complete date changed because action completed early. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-15-2025 04-15-2025 --- Yes
NOAA determines ESA Consultation Package is Complete - Informal (Agency Action) 06-13-2025 05-15-2025 --- Yes
ESA Consultation Concludes (Agency Action) 08-13-2025 08-13-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-15-2025 04-15-2025 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) --- --- --- No
NOAA determines ESA Consultation Package is Complete - Informal (Agency Action) 06-13-2025 06-13-2025 --- No
ESA Consultation Concludes (Agency Action) 08-13-2025 08-13-2025 --- No