USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
Current Target date for issuance of a decision changed because Agency issued decision a day early. Because the milestone was completed early the consultations to Executive Director and other agencies were not done. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 04-30-2025 04-30-2025 --- Yes
Completeness Determination (Agency Action) 05-30-2025 05-30-2025 --- Yes
Complete application submitted (Applicant Action) 06-20-2025 06-04-2025 --- Yes
Issuance of Decision (Agency Action) 07-29-2025 07-28-2025 --- Yes
In Progress
complete application received earlier than projected.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 04-30-2025 04-30-2025 --- Yes
Completeness Determination (Agency Action) 05-30-2025 05-30-2025 --- Yes
Complete application submitted (Applicant Action) 06-20-2025 06-04-2025 --- Yes
Issuance of Decision (Agency Action) 07-29-2025 07-29-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 04-30-2025 04-30-2025 --- Yes
Completeness Determination (Agency Action) 05-30-2025 05-30-2025 --- Yes
Complete application submitted (Applicant Action) 06-20-2025 06-20-2025 --- No
Issuance of Decision (Agency Action) 07-29-2025 07-29-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 04-30-2025 04-30-2025 --- Yes
Completeness Determination (Agency Action) 05-30-2025 05-30-2025 --- No
Complete application submitted (Applicant Action) --- --- --- No
Issuance of Decision (Agency Action) 07-29-2025 07-29-2025 --- No