Permitting Action Modification History

Complete
Completed milestones earlier than planned. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 02-28-2025 02-28-2025 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 03-21-2025 03-21-2025 --- Yes
Publication of Public Notice (Agency Action) 03-18-2025 03-18-2025 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 11-26-2025 09-16-2025 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 02-28-2025 02-28-2025 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 03-21-2025 03-21-2025 --- Yes
Publication of Public Notice (Agency Action) 03-18-2025 03-18-2025 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 11-26-2025 11-26-2025 --- No