Permitting Action Modification History
Modifications on 05/28/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 03-18-2025 | 03-18-2025 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 04-17-2025 | 04-17-2025 | --- | Yes |
Modifications on 05/09/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 03-18-2025 | 03-18-2025 | --- | Yes |
| Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) | --- | --- | --- | No |
| Section 106 consultation concluded (Agency Action) | 04-17-2025 | 04-17-2025 | --- | Yes |