Permitting Action Modification History

Complete
Completed milestones earlier than planned. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 03-21-2025 03-21-2025 --- Yes
Issuance of a Final EA (Agency Action) 11-25-2025 09-08-2025 --- Yes
EA Process Concluded (Agency Action) 11-25-2025 09-08-2025 --- Yes
In Progress
9 MAY 2025: Issuance of a Draft EA / Release for Public Review (Agency Action) was entered in error and is not a milestone. The lead agency does not have plans to release the draft EA for public comment and added a date when loading the timeline by mistake. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 03-21-2025 03-21-2025 --- Yes
Issuance of a Final EA (Agency Action) 11-25-2025 11-25-2025 --- No
EA Process Concluded (Agency Action) 11-25-2025 11-25-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 03-21-2025 03-21-2025 --- Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 11-11-2025 11-11-2025 --- No
Issuance of a Final EA (Agency Action) 11-25-2025 11-25-2025 --- No
Issuance of a Supplemental EA (Agency Action) --- --- --- No
EA Process Concluded (Agency Action) 11-25-2025 11-25-2025 --- No