Permitting Action Modification History

Planned
BIA coordinated with the project sponsor (Santa Fe Indian School) and the lead agency (NTIA) to adjust the milestone deadlines. We propose bumping Zuni Agency ROW (where construction is intended to begin first) out 6 months and bumping Ramah Agency and Southern Pueblos Agency ROWs out 9 months. This will provide sufficient time for SFIS to submit complete ROW applications and for legal review of recently submitted waivers for definite location. For further justification, please see the attached. As always, the NTIA and BIA are supportive of completing milestones earlier than the Dashboard deadlines. The BIA is prepared to process applications as soon as all required documents and materials are submitted. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 10-15-2025 07-13-2026 --- No
Application deemed complete (Agency Action) 12-31-2025 09-28-2026 --- No
Final decision/agency action (Agency Action) 01-31-2026 10-29-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 10-15-2025 10-15-2025 --- No
Application deemed complete (Agency Action) 12-31-2025 12-31-2025 --- No
Final decision/agency action (Agency Action) 01-31-2026 01-31-2026 --- No