Permitting Action Modification History

Planned
The applicant has asked to move the schedule back to align the state and federal review and permitting processes.  The applicant and EPA have been consulted. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Initial application received (Applicant Action) 03-31-2027 01-10-2028 No
Completed application received (Applicant Action) 04-30-2027 02-09-2028 No
Issuance of final decision/ permit approval (Agency Action) 07-29-2027 02-09-2029 No
Planned
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Initial application received (Applicant Action) --- 03-31-2027 No
Completed application received (Applicant Action) --- 04-30-2027 No
Issuance of final decision/ permit approval (Agency Action) --- 07-29-2027 No