Permitting Action Modification History

Complete
NOAA/NMFS signed the Biological Opinion 3 days ahead of schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-14-2025 07-14-2025 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 07-21-2025 07-17-2025 --- Yes
ESA Consultation Concludes (Agency Action) 11-03-2025 10-31-2025 --- Yes
In Progress
ESA consultation package determined complete earlier than scheduled. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-14-2025 07-14-2025 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 07-21-2025 07-17-2025 --- Yes
ESA Consultation Concludes (Agency Action) 11-03-2025 11-03-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-14-2025 07-14-2025 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 07-21-2025 07-21-2025 --- No
ESA Consultation Concludes (Agency Action) 11-03-2025 11-03-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-14-2025 07-14-2025 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 07-21-2025 07-21-2025 --- No
ESA Consultation Concludes (Agency Action) 11-03-2025 11-03-2025 --- No