USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Planned
NewRange has pushed their anticipated Section 404 permit application date from 29 MAY to 29 JULY 2026 due to ongoing land negotiations and non-disclosure agreements. The 404 Permit Application Date shift is resulting in a push of two months for all other actions., basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 11-28-2025 11-27-2026 No
Section 106 consultation concluded (Agency Action) 02-26-2026 02-24-2027 No
Planned
NewRange has pushed their anticipated Section 404 permit application date from 29 APR to 29 MAY 2026 due to ongoing land negotiations and non-disclosure agreements. Since the application receipt date affects the subsequent milestones, the remaining milestones have shifted to the right by a month as well. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 11-28-2025 09-28-2026 No
Section 106 consultation concluded (Agency Action) 02-26-2026 12-28-2026 No
Planned
NewRange has pushed their anticipated Section 404 permit application date from 12 MAR 2026 to 29 APR 2026 due to ongoing land negotiations and non-disclosure agreements. Since the application receipt date affects the subsequent milestones, the remaining milestones have shifted to the right by a month and a half as well. The table the current target dates and proposed dates to be updated in the Transparency Dashboard. NewRange concurred with the updated milestone dates, and the Corps has coordinated the updated timeline with all anticipated cooperating agencies. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 11-28-2025 08-27-2026 No
Section 106 consultation concluded (Agency Action) 02-26-2026 11-25-2026 No
Planned
NewRange has pushed their anticipated Section 404 permit application date from 28 JAN 2026 to 12 MAR 2026 due to ongoing land negotiations and non-disclosure agreements. Since the application receipt date affects the subsequent milestones, the remaining milestones have shifted to the right by a month and a half as well. The table below shows the current target dates and proposed dates to be updated in the Transparency Dashboard. NewRange concurred with the updated milestone dates, and the Corps has coordinated the updated timeline with all anticipated cooperating agencies. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 11-28-2025 07-10-2026 No
Section 106 consultation concluded (Agency Action) 02-26-2026 10-08-2026 No
Planned
The Corps has worked with NewRange to develop an aggressive approximate 14-month schedule (publication of NOI to ROD) for conducting a supplemental EIS (SEIS) and approximate 16 months to render a permit decision. This schedule is updating based on the permit application receival date of 11/28/2025, the need to conduct a SEIS, and a NOI publication date of 02/26/2026. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 11-28-2025 03-27-2026 No
Section 106 consultation concluded (Agency Action) 02-26-2026 06-26-2026 No
Planned
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) --- 11-28-2025 No
Section 106 consultation concluded (Agency Action) --- 02-26-2026 No