Permitting Action Modification History

Planned
NewRange has pushed their anticipated Section 404 permit application date from 29 MAY to 29 JULY 2026 due to ongoing land negotiations and non-disclosure agreements. The 404 Permit Application Date shift is resulting in a push of two months for all other actions., basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 11-28-2025 11-27-2026 No
FWS Requests Additional Information (Agency Action) 12-28-2025 12-28-2026 No
Lead Agency Responds to Additional Information Request (Agency Action) 01-28-2026 01-27-2027 No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 01-28-2026 02-10-2027 No
ESA Consultation Concludes (Agency Action) 06-12-2026 06-25-2027 No
Planned
NewRange has pushed their anticipated Section 404 permit application date from 29 APR to 29 MAY 2026 due to ongoing land negotiations and non-disclosure agreements. Since the application receipt date affects the subsequent milestones, the remaining milestones have shifted to the right by a month as well. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 11-28-2025 09-28-2026 No
FWS Requests Additional Information (Agency Action) 12-28-2025 10-28-2026 No
Lead Agency Responds to Additional Information Request (Agency Action) 01-28-2026 11-27-2026 No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 01-28-2026 12-11-2026 No
ESA Consultation Concludes (Agency Action) 06-12-2026 04-26-2027 No
Planned
NewRange has pushed their anticipated Section 404 permit application date from 12 MAR 2026 to 29 APR 2026 due to ongoing land negotiations and non-disclosure agreements. Since the application receipt date affects the subsequent milestones, the remaining milestones have shifted to the right by a month and a half as well. The table shows the current target dates and proposed dates to be updated in the Transparency Dashboard. NewRange concurred with the updated milestone dates, and the Corps has coordinated the updated timeline with all anticipated cooperating agencies. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 11-28-2025 08-27-2026 No
FWS Requests Additional Information (Agency Action) 12-28-2025 09-28-2026 No
Lead Agency Responds to Additional Information Request (Agency Action) 01-28-2026 10-28-2026 No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 01-28-2026 11-11-2026 No
ESA Consultation Concludes (Agency Action) 06-12-2026 03-26-2027 No
Planned
NewRange has pushed their anticipated Section 404 permit application date from 28 JAN 2026 to 12 MAR 2026 due to ongoing land negotiations and non-disclosure agreements. Since the application receipt date affects the subsequent milestones, the remaining milestones have shifted to the right by a month and a half as well. The table below shows the current target dates and proposed dates to be updated in the Transparency Dashboard. NewRange concurred with the updated milestone dates, and the Corps has coordinated the updated timeline with all anticipated cooperating agencies. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 11-28-2025 07-10-2026 No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 01-28-2026 09-22-2026 No
ESA Consultation Concludes (Agency Action) 06-12-2026 02-04-2027 No
Planned
The project sponsor requested a milestone date extension in submitting their Section 404 Clean Water Act application due to additional scoping need for the project. The new date extension date would push all subsequent project milestones out by at least 60 days. The new milestone dates are assuming that FWS determines that the package is complete. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 11-28-2025 05-28-2026 No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 01-28-2026 08-10-2026 No
ESA Consultation Concludes (Agency Action) 06-12-2026 12-23-2026 No
Planned
The Corps has worked with NewRange to develop an aggressive approximate 14-month schedule (publication of NOI to ROD) for conducting a supplemental EIS (SEIS) and approximate 16 months to render a permit decision. This schedule is updating based on the permit application receival date of 11/28/2025, the need to conduct a SEIS, and a NOI publication date of 02/26/2026. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 11-28-2025 03-27-2026 No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 01-28-2026 06-10-2026 No
ESA Consultation Concludes (Agency Action) 06-12-2026 10-23-2026 No
Planned
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- 11-28-2025 No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) --- 01-28-2026 No
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) --- 01-28-2026 No
ESA Consultation Concludes (Agency Action) --- 06-12-2026 No