Permitting Action Modification History
Modifications on 05/08/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 11-24-2010 | 11-24-2010 | Yes |
| Scoping (Agency Action) | 11-24-2010 | 11-24-2010 | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 03-15-2013 | 03-15-2013 | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 06-11-2027 | 06-11-2027 | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 11-12-2027 | 11-12-2027 | No |
Modifications on 06/12/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 11-24-2010 | 11-24-2010 | Yes |
| Scoping (Agency Action) | 11-24-2010 | 11-24-2010 | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 03-15-2013 | 03-15-2013 | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 06-11-2027 | 06-11-2027 | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 11-12-2027 | 11-12-2027 | No |
Modifications on 05/16/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | --- | 11-24-2010 | No |
| Scoping (Agency Action) | --- | 11-24-2010 | No |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | --- | 03-15-2013 | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | --- | 06-11-2027 | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | --- | 11-12-2027 | No |