Permitting Action Modification History

Cancelled
USACE has completed the jurisdictional determination and found that the project does not fall under federal jurisdiction, nor will it impact regulated waters of the U.S. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-21-2019 06-21-2019 Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-21-2019 08-21-2019 Yes
Publication of Public Notice (Agency Action) 09-06-2019 09-06-2019 Yes
Final Verification/Permit Decision Rendered (Agency Action) 02-13-2026 05-13-2026 No
In Progress
The Forest Service needs additional time to modify and issue Record of Decision to maintain alignment with objection instructions. The ROD delay will also delay this permit. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-21-2019 06-21-2019 Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-21-2019 08-21-2019 Yes
Publication of Public Notice (Agency Action) 09-06-2019 09-06-2019 Yes
Final Verification/Permit Decision Rendered (Agency Action) 02-13-2026 05-13-2026 No
In Progress
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-21-2019 06-21-2019 Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-21-2019 08-21-2019 Yes
Publication of Public Notice (Agency Action) 09-06-2019 09-06-2019 Yes
Final Verification/Permit Decision Rendered (Agency Action) 02-13-2026 02-13-2026 No