Permitting Action Modification History
Modifications on 05/20/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 07-27-2023 | 04-07-2023 | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 07-27-2023 | 07-27-2023 | Yes |
| Publication of Public Notice (Agency Action) | 08-08-2023 | 08-08-2023 | Yes |
| Final Verification/Permit Decision Rendered (Agency Action) | 05-30-2025 | 05-19-2025 | Yes |
Modifications on 05/09/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 07-27-2023 | 04-07-2023 | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 07-27-2023 | 07-27-2023 | Yes |
| Publication of Public Notice (Agency Action) | 08-08-2023 | 08-08-2023 | Yes |
| Final Verification/Permit Decision Rendered (Agency Action) | 05-30-2025 | 05-16-2025 | No |
Modifications on 05/05/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 07-27-2023 | 04-07-2023 | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 07-27-2023 | 07-27-2023 | Yes |
| Publication of Public Notice (Agency Action) | 08-08-2023 | 08-08-2023 | Yes |
| Final Verification/Permit Decision Rendered (Agency Action) | 05-30-2025 | 05-30-2025 | No |
Modifications on 05/05/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 07-27-2023 | 07-27-2023 | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 07-27-2023 | 07-27-2023 | Yes |
| Publication of Public Notice (Agency Action) | 08-08-2023 | 08-08-2023 | Yes |
| Final Verification/Permit Decision Rendered (Agency Action) | 05-30-2025 | 05-30-2025 | No |
Modifications on 05/05/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 07-27-2023 | 07-27-2023 | No |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 07-27-2023 | 07-27-2023 | Yes |
| Publication of Public Notice (Agency Action) | 08-08-2023 | 08-08-2023 | Yes |
| Final Verification/Permit Decision Rendered (Agency Action) | 05-30-2025 | 05-30-2025 | No |