Permitting Action Modification History
Modifications on 05/01/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | --- | 06-05-2017 | Yes |
| Scoping (Agency Action) | --- | 06-05-2017 | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | --- | 08-13-2020 | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | --- | 09-06-2024 | Yes |
| Official Notice of Availability of a Supplemental Draft EIS published in the FR (Agency Action) | --- | 10-28-2022 | Yes |
| Issuance of Lead Agency Record of Decision (Agency Action) | --- | 01-03-2025 | Yes |