Permitting Action Modification History
Modifications on 05/01/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | --- | 03-25-2024 | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | --- | 03-26-2024 | Yes |
| ESA Consultation Concludes (Agency Action) | --- | 09-05-2024 | Yes |