Permitting Action Modification History

Complete
Project dates adjusted to actual dates completed. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-15-2025 09-08-2025 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-08-2025 09-08-2025 Yes
ESA Consultation Concludes (Agency Action) 02-02-2026 09-19-2025 Yes
Planned
Project is ahead of schedule. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-15-2025 08-15-2025 No
ESA Consultation Concludes (Agency Action) 02-02-2026 10-16-2025 No
Planned
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- 08-15-2025 No
ESA Consultation Concludes (Agency Action) --- 02-02-2026 No