Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-18-2016 03-18-2016 Yes
Scoping (Agency Action) 03-18-2016 03-18-2016 Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-09-2019 08-09-2019 Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-20-2025 06-20-2025 Yes
Issuance of Lead Agency Record of Decision (Agency Action) 12-15-2025 03-16-2026 Yes
In Progress
The Forest Service requires additional time to review changes to the ROD as a result of objection instructions. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-18-2016 03-18-2016 Yes
Scoping (Agency Action) 03-18-2016 03-18-2016 Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-09-2019 08-09-2019 Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-20-2025 06-20-2025 Yes
Issuance of Lead Agency Record of Decision (Agency Action) 12-15-2025 03-16-2026 No
In Progress
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 03-18-2016 03-18-2016 Yes
Scoping (Agency Action) 03-18-2016 03-18-2016 Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-09-2019 08-09-2019 Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-20-2025 06-20-2025 Yes
Issuance of Lead Agency Record of Decision (Agency Action) 12-15-2025 12-15-2025 No
In Progress
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) --- 03-18-2016 Yes
Scoping (Agency Action) --- 03-18-2016 Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) --- 08-09-2019 Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) --- 06-20-2025 No
Issuance of Lead Agency Record of Decision (Agency Action) --- 12-15-2025 No