Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 07-06-2022 07-06-2022 Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 01-21-2025 01-21-2025 Yes
Issuance of a Final EA (Agency Action) 06-06-2025 06-23-2025 Yes
EA Process Concluded (Agency Action) 08-29-2025 10-03-2025 Yes
In Progress
The date was changed due to direction from the Regional Forester to provide the public time to comment on documents posted to the Forest website for the project. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 07-06-2022 07-06-2022 Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 01-21-2025 01-21-2025 Yes
Issuance of a Final EA (Agency Action) 06-06-2025 06-23-2025 Yes
EA Process Concluded (Agency Action) 08-29-2025 10-03-2025 No
In Progress
Change in date to reflect when the final FONSI will be signed, concluding the NEPA process. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 07-06-2022 07-06-2022 Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 01-21-2025 01-21-2025 Yes
Issuance of a Final EA (Agency Action) 06-06-2025 06-23-2025 Yes
EA Process Concluded (Agency Action) 08-29-2025 09-26-2025 No
In Progress
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 07-06-2022 07-06-2022 Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 01-21-2025 01-21-2025 Yes
Issuance of a Final EA (Agency Action) 06-06-2025 06-23-2025 Yes
EA Process Concluded (Agency Action) 08-29-2025 08-29-2025 No
In Progress
Minor shift in dates as local Forest experiences challenges with capacity changes. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 07-06-2022 07-06-2022 Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 01-21-2025 01-21-2025 Yes
Issuance of a Final EA (Agency Action) 06-06-2025 06-23-2025 No
EA Process Concluded (Agency Action) 08-29-2025 08-29-2025 No
In Progress
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 07-06-2022 07-06-2022 Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 01-21-2025 01-21-2025 Yes
Issuance of a Final EA (Agency Action) 06-06-2025 06-06-2025 No
EA Process Concluded (Agency Action) 08-29-2025 08-29-2025 No