Permitting Action Modification History

Complete
Entry error , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- 04-22-2025 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) --- 04-22-2025 Yes
ESA Consultation Concludes (Agency Action) --- 04-29-2025 Yes
Complete
Typo 0025 rather than 2025 , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- 04-22-2025 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) --- 04-29-2025 Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) --- --- No
ESA Consultation Concludes (Agency Action) --- --- No
Complete
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- 04-22-2025 Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) --- 04-29-0025 Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) --- --- No
ESA Consultation Concludes (Agency Action) --- --- No