Permitting Action Modification History

Complete
The field office received a project concurrence letter from the U.S. Fish and Wildlife Service on 5/8/2025, marking completion of the Endangered Species Act (DOI-FWS) consultation milestone for the Caldwell Canyon Mine Project. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-17-2025 03-17-2025 Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 03-17-2025 03-17-2025 Yes
ESA Consultation Concludes (Agency Action) 05-19-2025 05-08-2025 Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-17-2025 03-17-2025 Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 03-17-2025 03-17-2025 Yes
ESA Consultation Concludes (Agency Action) 05-19-2025 05-19-2025 No
Planned
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-17-2025 03-17-2025 Yes
ESA Consultation Concludes (Agency Action) 05-19-2025 05-19-2025 No