Permitting Action Modification History
Modifications on 02/27/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 02-28-2025 | 02-28-2025 | Yes |
| Scoping (Agency Action) | 03-31-2025 | 03-31-2025 | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 08-29-2025 | 08-29-2025 | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 01-30-2026 | 02-27-2026 | Yes |
| Issuance of Lead Agency Record of Decision (Agency Action) | 02-27-2026 | 02-27-2026 | Yes |
Modifications on 01/30/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 02-28-2025 | 02-28-2025 | Yes |
| Scoping (Agency Action) | 03-31-2025 | 03-31-2025 | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 08-29-2025 | 08-29-2025 | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 01-30-2026 | 02-27-2026 | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 02-27-2026 | 02-27-2026 | No |
Modifications on 09/19/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 02-28-2025 | 02-28-2025 | Yes |
| Scoping (Agency Action) | 03-31-2025 | 03-31-2025 | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 08-29-2025 | 08-29-2025 | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 01-30-2026 | 01-30-2026 | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 02-27-2026 | 02-27-2026 | No |
Modifications on 04/30/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | --- | 02-28-2025 | Yes |
| Scoping (Agency Action) | --- | 03-31-2025 | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | --- | 08-29-2025 | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | --- | 01-30-2026 | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | --- | 02-27-2026 | No |