Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 05-28-2024 05-28-2024 Yes
Scoping (Agency Action) 06-13-2024 06-13-2024 Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 03-06-2026 10-16-2025 Yes
Issuance of Lead Agency Record of Decision (Agency Action) 05-04-2026 10-16-2025 Yes
In Progress
This project is proceeding under the new NEPA regulations and will not be doing a Draft EIS/comment period. Project is ahead of schedule. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 05-28-2024 05-28-2024 Yes
Scoping (Agency Action) 06-13-2024 06-13-2024 Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 03-06-2026 10-16-2025 No
Issuance of Lead Agency Record of Decision (Agency Action) 05-04-2026 10-16-2025 No
In Progress
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 05-28-2024 05-28-2024 Yes
Scoping (Agency Action) 06-13-2024 06-13-2024 Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-29-2025 08-29-2025 No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 03-06-2026 03-06-2026 No
Issuance of Lead Agency Record of Decision (Agency Action) 05-04-2026 05-04-2026 No
In Progress
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) --- 05-28-2024 Yes
Scoping (Agency Action) --- 06-13-2024 No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) --- 08-29-2025 No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) --- 03-06-2026 No
Issuance of Lead Agency Record of Decision (Agency Action) --- 05-04-2026 No