Permitting Action Modification History
Modifications on 10/16/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 11-22-2023 | 11-22-2023 | Yes |
| Scoping (Agency Action) | 12-22-2023 | 12-22-2023 | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 12-20-2024 | 12-20-2024 | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 09-05-2025 | 10-16-2025 | Yes |
| Issuance of Lead Agency Record of Decision (Agency Action) | 10-15-2025 | 10-16-2025 | Yes |
Modifications on 09/17/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 11-22-2023 | 11-22-2023 | Yes |
| Scoping (Agency Action) | 12-22-2023 | 12-22-2023 | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 12-20-2024 | 12-20-2024 | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 09-05-2025 | 10-15-2025 | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 10-15-2025 | 10-15-2025 | No |
Modifications on 04/30/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | --- | 11-22-2023 | Yes |
| Scoping (Agency Action) | --- | 12-22-2023 | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | --- | 12-20-2024 | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | --- | 09-05-2025 | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | --- | 10-15-2025 | No |