Permitting Action Modification History

In Progress
Applicant needs additional time to provide required information. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Initial application submitted (Applicant Action) 12-30-2022 12-30-2022 Yes
Application deemed complete (Agency Action) 02-21-2024 02-21-2024 Yes
Final decision/agency action (Agency Action) 08-31-2025 02-05-2027 No
In Progress
Applicant needs additional time to complete permitting requirements. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Initial application submitted (Applicant Action) 12-30-2022 12-30-2022 Yes
Application deemed complete (Agency Action) 02-21-2024 02-21-2024 Yes
Final decision/agency action (Agency Action) 08-31-2025 10-02-2026 No
In Progress
Project sponsor requires additional time to secure permits. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Initial application submitted (Applicant Action) 12-30-2022 12-30-2022 Yes
Application deemed complete (Agency Action) 02-21-2024 02-21-2024 Yes
Final decision/agency action (Agency Action) 08-31-2025 05-29-2026 No
In Progress
Applicant needs additional time to re-submit permit applications. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Initial application submitted (Applicant Action) 12-30-2022 12-30-2022 Yes
Application deemed complete (Agency Action) 02-21-2024 02-21-2024 Yes
Final decision/agency action (Agency Action) 08-31-2025 12-31-2025 No
In Progress
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Initial application submitted (Applicant Action) 12-30-2022 12-30-2022 Yes
Application deemed complete (Agency Action) 02-21-2024 02-21-2024 Yes
Final decision/agency action (Agency Action) 08-31-2025 08-31-2025 No