USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
USACE completed earlier than target date
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 09-29-2025 09-29-2025 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 10-13-2025 10-09-2025 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 12-29-2025 12-16-2025 --- Yes
In Progress
NANA worked with USACE to provide a complete application ahead of the 10/13/2025 milestone.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 09-29-2025 09-29-2025 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 10-13-2025 10-09-2025 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 12-29-2025 12-29-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 09-29-2025 09-29-2025 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 10-13-2025 10-13-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 12-29-2025 12-29-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 09-29-2025 09-29-2025 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 10-13-2025 10-13-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 12-29-2025 12-29-2025 --- No