Permitting Action Modification History

Complete
USACE completed earlier than target date , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 09-29-2025 09-29-2025 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 10-13-2025 10-09-2025 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 12-29-2025 12-16-2025 --- Yes
In Progress
NANA worked with USACE to provide a complete application ahead of the 10/13/2025 milestone. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 09-29-2025 09-29-2025 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 10-13-2025 10-09-2025 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 12-29-2025 12-29-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 09-29-2025 09-29-2025 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 10-13-2025 10-13-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 12-29-2025 12-29-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 09-29-2025 09-29-2025 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 10-13-2025 10-13-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 12-29-2025 12-29-2025 --- No