Permitting Action Modification History
Modifications on 04/16/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 03-28-2025 | 03-28-2025 | --- | Yes |
| Application deemed complete (Agency Action) | 07-28-2025 | 07-28-2025 | --- | Yes |
| Final decision/agency action (Agency Action) | 04-15-2026 | 04-15-2026 | --- | Yes |
Modifications on 07/28/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 03-28-2025 | 03-28-2025 | --- | Yes |
| Application deemed complete (Agency Action) | 07-28-2025 | 07-28-2025 | --- | Yes |
| Final decision/agency action (Agency Action) | 04-15-2026 | 04-15-2026 | --- | No |
Modifications on 05/09/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 03-28-2025 | 03-28-2025 | --- | Yes |
| Application deemed complete (Agency Action) | 07-28-2025 | 07-28-2025 | --- | No |
| Final decision/agency action (Agency Action) | 04-15-2026 | 04-15-2026 | --- | No |