Permitting Action Modification History

Complete
The FONSI was signed and the EA finalized ahead of the 12/26/25 milestone.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 05-09-2025 05-09-2025 --- Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 10-15-2025 10-15-2025 --- Yes
Issuance of a Final EA (Agency Action) 12-26-2025 12-18-2025 --- Yes
EA Process Concluded (Agency Action) 12-26-2025 12-18-2025 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 05-09-2025 05-09-2025 --- Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 10-15-2025 10-15-2025 --- Yes
Issuance of a Final EA (Agency Action) 12-26-2025 12-26-2025 --- No
EA Process Concluded (Agency Action) 12-26-2025 12-26-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 05-09-2025 05-09-2025 --- Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 10-15-2025 10-15-2025 --- No
Issuance of a Final EA (Agency Action) 12-26-2025 12-26-2025 --- No
EA Process Concluded (Agency Action) 12-26-2025 12-26-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 05-09-2025 05-09-2025 --- No
Issuance of a Draft EA / Release for Public Review (Agency Action) 10-15-2025 10-15-2025 --- No
Issuance of a Final EA (Agency Action) 12-26-2025 12-26-2025 --- No
EA Process Concluded (Agency Action) 12-26-2025 12-26-2025 --- No