USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Cancelled
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 10-29-2027 10-29-2027 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-29-2027 11-29-2027 --- No
ESA Consultation Concludes (Agency Action) 04-12-2028 04-12-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 10-29-2027 10-29-2027 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 11-29-2027 11-29-2027 --- No
ESA Consultation Concludes (Agency Action) 04-12-2028 04-12-2028 --- No