Permitting Action Modification History

Planned
As part of BLM’s effort to align with the Department of the Interior’s July 15, 2025 memorandum, updates to the Mosey Solar Project schedule, including updating the milestone dates on the FAST-41 Dashboard, are necessary to comply with the new requirement that all wind and solar energy project decisions, actions, consultations, and other undertakings be routed through the Office of the Secretary for final review prior to the agency taking action. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-07-2026 01-15-2027 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 12-21-2026 03-16-2027 --- No
ESA Consultation Concludes (Agency Action) 08-06-2027 12-17-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-07-2026 08-07-2026 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 12-21-2026 12-21-2026 --- No
ESA Consultation Concludes (Agency Action) 08-06-2027 08-06-2027 --- No