USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 07-01-2024 07-01-2024 --- Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 02-05-2025 02-05-2025 --- Yes
Issuance of a Final EA (Agency Action) 03-25-2025 03-24-2025 --- Yes
EA Process Concluded (Agency Action) 04-24-2025 04-24-2025 --- Yes
In Progress
Final EA was published on March 24, 2025, one day ahead of schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 07-01-2024 07-01-2024 --- Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 02-05-2025 02-05-2025 --- Yes
Issuance of a Final EA (Agency Action) 03-25-2025 03-24-2025 --- Yes
EA Process Concluded (Agency Action) 04-24-2025 04-24-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 07-01-2024 07-01-2024 --- Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 02-05-2025 02-05-2025 --- Yes
Issuance of a Final EA (Agency Action) 03-25-2025 03-25-2025 --- No
EA Process Concluded (Agency Action) 04-24-2025 04-24-2025 --- No