Permitting Action Modification History

Paused
To ensure the effective administration of public lands, the Bureau of Land Management (BLM) proposes extending the publication of the Notice of Intent in the Federal Register to October 29, 2027. This extension is necessary to provide the project sponsor, Balanced Rock Power, with additional time to engage meaningfully with grazing permittees and address grazing impacts identified during the variance process. These changes create a cascading effect for all other actions, such as Section 106 Review, consultation concluded.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 02-28-2025 02-26-2025 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 02-28-2025 02-26-2025 --- Yes
Section 106 consultation concluded (Agency Action) 06-01-2026 06-01-2026 --- No
In Progress
Consultation initiation letters to SHPOs/THPOs including notification that the agency will use NEPA substitution approach were signed and mailed to the appropriate agencies on 2/26/2025. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 02-28-2025 02-26-2025 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 02-28-2025 02-26-2025 --- Yes
Section 106 consultation concluded (Agency Action) 06-01-2026 06-01-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 02-28-2025 02-28-2025 --- No
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 02-28-2025 02-28-2025 --- No
Section 106 consultation concluded (Agency Action) 06-01-2026 06-01-2026 --- No