Permitting Action Modification History

Complete
Bureau of Indian Affairs completed the milestone on 4/8/26, ahead of scheduled milestone target date (4/30/26). , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-31-2025 02-14-2025 --- Yes
Application deemed complete (Agency Action) 11-17-2025 01-06-2026 --- Yes
Final decision/agency action (Agency Action) 12-23-2025 04-08-2026 --- Yes
In Progress
Milestone completed earlier than anticipated. Target dated changed from 3/17/2026 to 1/6/2026. Preliminary review indicates that the ROW application submitted on December 23, 2025 is missing several required items and/or documents as outlined on 25 CFR 169.101. However, will consider this submission complete with the expectation that all outstanding information and documentation will be submitted to our office within 30 calendar days from the date of this letter. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-31-2025 02-14-2025 --- Yes
Application deemed complete (Agency Action) 11-17-2025 01-06-2026 --- Yes
Final decision/agency action (Agency Action) 12-23-2025 04-30-2026 --- No
Planned
This extension would allow the proponent time to submit required documentation (survey plats and Joint Use Agreement/Permits for ROW). A detailed survey plat and legal description of where the proposed right of way will be within the existing easements are necessary, to ensure accuracy and to show that all the requirements of the legal description have been met. Given the application is not yet complete, all milestones will need to be pushed out. Coordination with all cooperating agencies on these milestone changes has occurred.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-31-2025 02-14-2025 --- Yes
Application deemed complete (Agency Action) 11-17-2025 03-17-2026 --- No
Final decision/agency action (Agency Action) 12-23-2025 04-30-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-31-2025 02-14-2025 --- Yes
Application deemed complete (Agency Action) 11-17-2025 11-17-2025 --- No
Final decision/agency action (Agency Action) 12-23-2025 12-23-2025 --- No
Planned
After detailed discussions with the agency, the project sponsor needs additional time to prepare and submit the initial application. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-31-2025 02-14-2025 --- No
Application deemed complete (Agency Action) 11-17-2025 11-17-2025 --- No
Final decision/agency action (Agency Action) 12-23-2025 12-23-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-31-2025 01-31-2025 --- No
Application deemed complete (Agency Action) 11-17-2025 11-17-2025 --- No
Final decision/agency action (Agency Action) 12-23-2025 12-23-2025 --- No