Permitting Action Modification History

Cancelled
BIA determined that no BLM actions were needed on Phase 1 of the NNDOE project., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 01-31-2025 01-27-2025 --- Yes
Completed application received (Agency Action) 11-17-2025 03-17-2026 --- Yes
Final decision/agency action (Agency Action) 12-23-2025 04-30-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 01-31-2025 01-27-2025 --- Yes
Completed application received (Agency Action) 11-17-2025 03-17-2026 --- Yes
Final decision/agency action (Agency Action) 12-23-2025 04-30-2026 --- No
In Progress
This extension would allow the proponent time to submit required documentation (survey plats and Joint Use Agreement/Permits for ROW). A detailed survey plat and legal description of where the proposed right of way will be within the existing easements are necessary, to ensure accuracy and to show that all the requirements of the legal description have been met. Given the application is not yet complete, all milestones will need to be pushed out. Coordination with all cooperating agencies on these milestone changes has occurred.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 01-31-2025 01-27-2025 --- Yes
Completed application received (Agency Action) 11-17-2025 03-17-2026 --- No
Final decision/agency action (Agency Action) 12-23-2025 04-30-2026 --- No
In Progress
Milestone met ahead of schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 01-31-2025 01-27-2025 --- Yes
Completed application received (Agency Action) 11-17-2025 11-17-2025 --- No
Final decision/agency action (Agency Action) 12-23-2025 12-23-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 01-31-2025 01-31-2025 --- No
Completed application received (Agency Action) 11-17-2025 11-17-2025 --- No
Final decision/agency action (Agency Action) 12-23-2025 12-23-2025 --- No