Permitting Action Modification History

Complete
Letter of concurrence was issued by FWS ahead of schedule.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 02-06-2025 09-08-2025 --- Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 12-17-2025 12-17-2025 --- Yes
ESA Consultation Concludes (Agency Action) 07-21-2025 02-20-2026 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 02-06-2025 09-08-2025 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 03-06-2025 12-17-2025 --- Yes
ESA Consultation Concludes (Agency Action) 07-21-2025 02-23-2026 --- No
In Progress
The milestone target was scheduled for October 8, 2025. Realignment of the project scope due to changes requested by the project sponsor required a revision to the BA. BIA revised the BA to reflect the changes and resubmitted to FWS on December 12. The application was deemed complete by FWS on December 17.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 02-06-2025 09-08-2025 --- Yes
ESA Consultation Concludes (Agency Action) 07-21-2025 02-23-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 02-06-2025 09-08-2025 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 03-06-2025 10-08-2025 --- No
ESA Consultation Concludes (Agency Action) 07-21-2025 02-23-2026 --- No
Planned
This extension would allow the proponent time to submit required documentation (survey plats and Joint Use Agreement/Permits for ROW). A detailed survey plat and legal description of where the proposed right of way will be within the existing easements are necessary, to ensure accuracy and to show that all the requirements of the legal description have been met. Given the application is not yet complete, all milestones will need to be pushed out. Coordination with all cooperating agencies on these milestone changes has occurred.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 02-06-2025 09-08-2025 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 03-06-2025 10-08-2025 --- No
ESA Consultation Concludes (Agency Action) 07-21-2025 02-23-2026 --- No
Planned
Project sponsor needs more time to submit the necessary information to BIA and cooperating agencies for development and submittal of a request for ESA consultation to FWS. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 02-06-2025 03-06-2025 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 03-06-2025 04-04-2025 --- No
ESA Consultation Concludes (Agency Action) 07-21-2025 08-20-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 02-06-2025 02-06-2025 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 03-06-2025 03-06-2025 --- No
ESA Consultation Concludes (Agency Action) 07-21-2025 07-21-2025 --- No