Permitting Action Modification History

Complete
EA milestones completed early by the authorizing agency.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 01-31-2025 01-28-2025 --- Yes
Issuance of a Final EA (Agency Action) 11-24-2025 02-10-2026 --- Yes
EA Process Concluded (Agency Action) 12-23-2025 02-10-2026 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 01-31-2025 01-28-2025 --- Yes
Issuance of a Final EA (Agency Action) 11-24-2025 03-25-2026 --- No
EA Process Concluded (Agency Action) 12-23-2025 04-30-2026 --- No
In Progress
This extension would allow the proponent time to submit required documentation (survey plats and Joint Use Agreement/Permits for ROW). A detailed survey plat and legal description of where the proposed right of way will be within the existing easements are necessary, to ensure accuracy and to show that all the requirements of the legal description have been met. Given the application is not yet complete, all milestones will need to be pushed out. Coordination with all cooperating agencies on these milestone changes has occurred.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 01-31-2025 01-28-2025 --- Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 10-20-2025 12-30-2025 --- No
Issuance of a Final EA (Agency Action) 11-24-2025 03-25-2026 --- No
EA Process Concluded (Agency Action) 12-23-2025 04-30-2026 --- No
In Progress
Determination made ahead of schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 01-31-2025 01-28-2025 --- Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 10-20-2025 10-20-2025 --- No
Issuance of a Final EA (Agency Action) 11-24-2025 11-24-2025 --- No
EA Process Concluded (Agency Action) 12-23-2025 12-23-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 01-31-2025 01-31-2025 --- No
Issuance of a Draft EA / Release for Public Review (Agency Action) 10-20-2025 10-20-2025 --- No
Issuance of a Final EA (Agency Action) 11-24-2025 11-24-2025 --- No
EA Process Concluded (Agency Action) 12-23-2025 12-23-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 01-31-2025 01-31-2025 --- No
Issuance of a Draft EA / Release for Public Review (Agency Action) 10-20-2025 10-20-2025 --- No
Issuance of a Final EA (Agency Action) 11-24-2025 11-24-2025 --- No
Issuance of a Supplemental EA (Agency Action) --- --- --- No
EA Process Concluded (Agency Action) 12-23-2025 12-23-2025 --- No