Permitting Action Modification History

Cancelled
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 11-23-2026 05-22-2028 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 04-20-2027 11-14-2028 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 07-19-2027 02-12-2029 --- No
Planned
The project sponsor submitted an updated Construction and Operations Plan (COP) to BOEM on September 29, 2025. On October 1, 2025 the government shut down through November 12, 2025, impacting BOEM’s ability to review the COP submission. In addition, multiple comments were not addressed by the project sponsor in their September 29, 2025 COP submission and the project sponsor indicated that the Underwater Acoustic Assessment, Historic Resources Visual Effects Assessment, and Seascape and Landscape Visual Impact Assessment and associated COP updates would be submitted later in time. BOEM expects a third and fourth COP submission prior to BOEM’s issuance of an NOI. Therefore, BOEM is shifting the completion of the Agency Review of Updated Application for Consistency with NOI Checklist milestone from November 28, 2025 to February 2, 2026, which affects the rest of the NEPA schedule and NMFS milestones were revised accordingly. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 11-23-2026 05-22-2028 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 04-20-2027 11-14-2028 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 07-19-2027 02-12-2029 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 11-23-2026 11-23-2026 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 04-20-2027 04-20-2027 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 07-19-2027 07-19-2027 --- No