USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Cancelled
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 11-23-2026 05-22-2028 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 04-20-2027 11-14-2028 --- No
ESA Consultation Concludes (Agency Action) 09-17-2027 04-13-2029 --- No
Planned
The project sponsor submitted an updated Construction and Operations Plan (COP) to BOEM on September 29, 2025. On October 1, 2025 the government shut down through November 12, 2025, impacting BOEM’s ability to review the COP submission. In addition, multiple comments were not addressed by the project sponsor in their September 29, 2025 COP submission and the project sponsor indicated that the Underwater Acoustic Assessment, Historic Resources Visual Effects Assessment, and Seascape and Landscape Visual Impact Assessment and associated COP updates would be submitted later in time. BOEM expects a third and fourth COP submission prior to BOEM’s issuance of an NOI. Therefore, BOEM is shifting the completion of the Agency Review of Updated Application for Consistency with NOI Checklist milestone from November 28, 2025 to February 2, 2026 and completion of the Applicant Submits Updated Application for Consistency with the NOI Checklist from December 5, 2025 to May 28, 2027, which affects the rest of the NEPA schedule and NMFS milestones were revised accordingly. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 11-23-2026 05-22-2028 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 04-20-2027 11-14-2028 --- No
ESA Consultation Concludes (Agency Action) 09-17-2027 04-13-2029 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 11-23-2026 11-23-2026 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 04-20-2027 04-20-2027 --- No
ESA Consultation Concludes (Agency Action) 09-17-2027 09-17-2027 --- No