Permitting Action Modification History

Cancelled
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 01-27-2026 01-27-2026 07-27-2027 No
Scoping (Agency Action) 02-27-2026 02-27-2026 08-26-2027 No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 02-19-2027 02-19-2027 09-15-2028 No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 12-03-2027 12-03-2027 06-29-2029 No
Issuance of Lead Agency Record of Decision (Agency Action) 01-18-2028 01-18-2028 08-13-2029 No
Planned
BOEM is requesting these completion date modifications due to the government shutdown and the timing of the Project Sponsor’s submissions of the revised Construction and Operations Plan (COP) containing information that BOEM requires prior to issuing a Notice of Intent (NOI) to prepare an Environmental Impact Statement (EIS) under NEPA. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 01-27-2026 01-27-2026 07-27-2027 No
Scoping (Agency Action) 02-27-2026 02-27-2026 08-26-2027 No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 02-19-2027 02-19-2027 09-15-2028 No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 12-03-2027 12-03-2027 06-29-2029 No
Issuance of Lead Agency Record of Decision (Agency Action) 01-18-2028 01-18-2028 08-13-2029 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 01-27-2026 01-27-2026 --- No
Scoping (Agency Action) 02-27-2026 02-27-2026 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 02-19-2027 02-19-2027 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 12-03-2027 12-03-2027 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 01-18-2028 01-18-2028 --- No