Permitting Action Modification History

Cancelled
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 09-20-2024 09-20-2024 --- Yes
Application deemed complete (Agency Action) 05-30-2025 05-19-2025 --- Yes
Final decision/agency action (Agency Action) 03-17-2028 10-12-2029 --- No
In Progress
The project sponsor submitted an updated COP to BOEM on September 29, 2025. On October 1, 2025, the government shut down through November 12, 2025, impacting BOEM’s ability to review the COP submission. In addition, multiple agency comments were not addressed by the project sponsor in their September 29, 2025 COP submission and the project sponsor indicated that the Underwater Acoustic Assessment, Historic Resources Visual Effects Assessment, and Seascape and Landscape Visual Impact Assessment and associated COP updates would be submitted later in time. BOEM expects a third and fourth COP submission prior to BOEM’s issuance of an NOI. Therefore, BOEM is shifting the completion of the Agency Review of Updated Application for Consistency with NOI Checklist milestone from November 28, 2025 to February 2, 2026 and completion of the Applicant Submits Updated Application for Consistency with the NOI Checklist from December 5, 2025 to May 28, 2027. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 09-20-2024 09-20-2024 --- Yes
Application deemed complete (Agency Action) 05-30-2025 05-19-2025 --- Yes
Final decision/agency action (Agency Action) 03-17-2028 10-12-2029 --- No
In Progress
BOEM's completeness review of the April 30, 2025 COP was completed on May 19, 2025. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 09-20-2024 09-20-2024 --- Yes
Application deemed complete (Agency Action) 05-30-2025 05-19-2025 --- Yes
Final decision/agency action (Agency Action) 03-17-2028 03-17-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 09-20-2024 09-20-2024 --- Yes
Application deemed complete (Agency Action) 05-30-2025 05-30-2025 --- No
Final decision/agency action (Agency Action) 03-17-2028 03-17-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 09-20-2024 09-20-2024 --- No
Application deemed complete (Agency Action) 05-30-2025 05-30-2025 --- No
Final decision/agency action (Agency Action) 03-17-2028 03-17-2028 --- No