Permitting Action Modification History

Planned
The MMPA milestones "Publish Proposed ITA in the Federal Register” and “Publish Final ITA Regulations in Federal Register” are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to these MMPA action milestones.  Therefore, an extension is requested based upon the extension of BOEM’s EIS milestones. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 06-12-2025 06-12-2025 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 12-12-2025 12-07-2026 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 01-13-2026 01-11-2027 --- No
Publish Proposed ITA in Federal Register (Agency Action) 08-13-2026 08-09-2027 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 07-30-2027 07-26-2028 --- No
ITA decision rendered (Agency Action) 08-30-2027 08-28-2028 --- No
Planned
The MMPA milestones "Publish Proposed ITA in the Federal Register” and “Publish Final ITA Regulations in Federal Register” are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to these MMPA action milestones. Therefore, an extension is requested based upon the extension of BOEM’s EIS milestones. The requested milestone changes are shown in the table below. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 06-12-2025 06-12-2025 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 12-12-2025 06-10-2026 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 01-13-2026 07-13-2026 --- No
Publish Proposed ITA in Federal Register (Agency Action) 08-13-2026 02-09-2027 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 07-30-2027 01-28-2028 --- No
ITA decision rendered (Agency Action) 08-30-2027 02-28-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 06-12-2025 06-12-2025 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 12-12-2025 12-12-2025 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 01-13-2026 01-13-2026 --- No
Publish Proposed ITA in Federal Register (Agency Action) 08-13-2026 08-13-2026 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 07-30-2027 07-30-2027 --- No
ITA decision rendered (Agency Action) 08-30-2027 08-30-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 06-12-2025 06-12-2025 --- No
NOAA Determines ITA Application is Complete (Applicant Action) 12-12-2025 12-12-2025 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 01-13-2026 01-13-2026 --- No
Publish Proposed ITA in Federal Register (Agency Action) 08-13-2026 08-13-2026 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 07-30-2027 07-30-2027 --- No
ITA decision rendered (Agency Action) 08-30-2027 08-30-2027 --- No