USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Planned
The EFH milestones "NOAA Determines EFH Assessment is Complete" and “NOAA Issues any EFH Conservation Recommendations" are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to these EFH action milestones.  Therefore, an extension of the EFH milestones is requested based upon the extension of BOEM’s EIS milestones. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 03-11-2026 03-08-2027 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 08-13-2026 08-09-2027 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 11-12-2026 11-08-2027 --- No
Planned
The EFH milestones "NOAA Determines EFH Assessment is Complete" and “NOAA Issues any EFH Conservation Recommendations" are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to these EFH action milestones.  Therefore, an extension of the EFH milestones is requested based upon the extension of BOEM’s EIS milestones. The requested milestone changes are shown in the table below. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 03-11-2026 09-07-2026 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 08-13-2026 02-09-2027 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 11-12-2026 05-11-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 03-11-2026 03-11-2026 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 08-13-2026 08-13-2026 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 11-12-2026 11-12-2026 --- No