Permitting Action Modification History

Planned
The ESA milestones "NOAA Determines ESA Consultation Package is Complete - Formal" and "ESA Consultation Concludes" are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to these ESA action milestones.  Therefore, an extension is requested based upon the extension of BOEM’s EIS milestones. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-11-2026 03-08-2027 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 08-13-2026 08-09-2027 --- No
ESA Consultation Concludes (Agency Action) 01-11-2027 01-10-2028 --- No
Planned
The ESA milestones "NOAA Determines ESA Consultation Package is Complete - Formal" and "ESA Consultation Concludes" are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to these ESA action milestones. Therefore, an extension is requested based upon the extension of BOEM’s EIS milestones. The requested milestone changes are shown in the table below. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-11-2026 09-07-2026 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 08-13-2026 02-09-2027 --- No
ESA Consultation Concludes (Agency Action) 01-11-2027 07-12-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-11-2026 03-11-2026 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 08-13-2026 08-13-2026 --- No
ESA Consultation Concludes (Agency Action) 01-11-2027 01-11-2027 --- No