Permitting Action Modification History

Planned
The Section 408 milestones are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to the Section 408 action milestones.  Therefore, an extension of the Section 408 milestones is requested based upon the extension of BOEM’s EIS milestones. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 04-28-2026 04-26-2027 --- No
Completeness Determination (Agency Action) 05-28-2026 05-24-2027 --- No
Complete application submitted (Applicant Action) 04-01-2027 03-27-2028 --- No
Issuance of Decision (Agency Action) 08-30-2027 09-25-2028 --- No
Planned
The Section 408 milestones are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to the Section 408 action milestones. Therefore, an extension of the Section 408 milestones is requested based upon the extension of BOEM’s EIS milestones. The requested milestone changes are shown in the table below. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 04-28-2026 10-26-2026 --- No
Completeness Determination (Agency Action) 05-28-2026 11-24-2026 --- No
Complete application submitted (Applicant Action) 04-01-2027 09-28-2027 --- No
Issuance of Decision (Agency Action) 08-30-2027 03-28-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 04-28-2026 04-28-2026 --- No
Completeness Determination (Agency Action) 05-28-2026 05-28-2026 --- No
Complete application submitted (Applicant Action) 04-01-2027 04-01-2027 --- No
Issuance of Decision (Agency Action) 08-30-2027 08-30-2027 --- No