Permitting Action Modification History

Planned
The Section 10/404 milestones are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to the Section 10/404 action milestones. Therefore, an extension of the Section 10/404 milestones is requested based upon the extension of BOEM’s EIS milestones. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-28-2026 04-26-2027 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 05-28-2026 05-24-2027 --- No
Publication of Public Notice (Agency Action) 06-12-2026 06-07-2027 --- No
Final Verification/Permit Decision Rendered (Agency Action) 08-30-2027 09-25-2028 --- No
Planned
The Section 10/404 milestones are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 180 days results in a commensurate shift to the Section 10/404 action milestones. Therefore, an extension of the Section 10/404 milestones is requested based upon the extension of BOEM’s EIS milestones. The requested milestone changes are shown in the table below. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-28-2026 10-26-2026 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 05-28-2026 11-24-2026 --- No
Publication of Public Notice (Agency Action) 06-12-2026 12-09-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 08-30-2027 03-28-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-28-2026 04-28-2026 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 05-28-2026 05-28-2026 --- No
Publication of Public Notice (Agency Action) 06-12-2026 06-12-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 08-30-2027 08-30-2027 --- No