Permitting Action Modification History

In Progress
The COP final decision/agency action milestone is dependent on the NEPA timeline and affected commensurately by delays., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-25-2024 01-25-2024 --- Yes
Application deemed complete (Agency Action) 02-05-2024 02-05-2024 --- Yes
Final decision/agency action (Agency Action) 08-30-2027 08-28-2028 --- No
In Progress
The COP final decision/agency action milestone is dependent on the NEPA timeline and affected commensurately by delays; this 180-day shift is shown in the table below. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-25-2024 01-25-2024 --- Yes
Application deemed complete (Agency Action) 02-05-2024 02-05-2024 --- Yes
Final decision/agency action (Agency Action) 08-30-2027 02-28-2028 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 01-25-2024 01-25-2024 --- Yes
Application deemed complete (Agency Action) 02-05-2024 02-05-2024 --- Yes
Final decision/agency action (Agency Action) 08-30-2027 08-30-2027 --- No