Permitting Action Modification History

In Progress
The “Section 106 consultation concluded” milestone is dependent on the timing of consultation meetings with consulting parties – critical milestones in the projects permitting table. The revised schedule reflects the time necessary for BOEM to conduct thorough and meaningful consultation in accordance with the National Historic Preservation Act (NHPA), while fully complying with any applicable departmental procedures., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-15-2025 01-15-2025 --- Yes
Section 106 consultation concluded (Agency Action) 04-16-2027 04-10-2028 --- No
In Progress
The “Section 106 consultation concluded” milestone is dependent on the timing of consultation meetings with consulting parties – critical milestones in the projects permitting table. The revised schedule reflects the time necessary for BOEM to conduct thorough and meaningful consultation in accordance with the National Historic Preservation Act (NHPA), while fully complying with any applicable departmental procedures. This 180-day shift is shown in the table below. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-15-2025 01-15-2025 --- Yes
Section 106 consultation concluded (Agency Action) 04-16-2027 10-13-2027 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-15-2025 01-15-2025 --- Yes
Section 106 consultation concluded (Agency Action) 04-16-2027 04-16-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-15-2025 01-15-2025 --- No
Section 106 consultation concluded (Agency Action) 04-16-2027 04-16-2027 --- No