USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

In Progress
The explanation for the milestone date change is outlined in the Executive Director Determination posted on the project page. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 08-05-2020 08-05-2020 --- Yes
Final decision/agency action (Agency Action) 03-09-2027 04-02-2027 --- No
In Progress
The revised schedule extends the BLMs target dates for issuance of the National Environmental Policy Act (NEPA) documents and the final order by approximately 42 days. The shift for the ROW grant shifts 60 days to accommodate internal reviews and approval. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 08-05-2020 08-05-2020 --- Yes
Final decision/agency action (Agency Action) 03-09-2027 03-09-2027 --- No
In Progress
The explanation for the milestone date change is outlined in the Executive Director Determination posted on the project page. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 08-05-2020 08-05-2020 --- Yes
Final decision/agency action (Agency Action) 03-09-2027 04-02-2027 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 08-05-2020 08-05-2020 --- Yes
Final decision/agency action (Agency Action) 03-09-2027 03-09-2027 --- No