Permitting Action Modification History

Paused
To ensure the effective administration of public lands, the Bureau of Land Management (BLM) proposes extending the publication of the Notice of Intent in the Federal Register to September 24, 2027. This extension is necessary to provide the project sponsor, Arevia Power, with additional time to engage meaningfully with grazing permittees and address grazing impacts identified during the variance process. Additional time is also required to coordinate with the adjacent project sponsor, Balanced Rock Power, to resolve access issues affecting both projects. The Plan of Development and associated application will need to be revised and resubmitted to reflect these resolutions.  
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 08-05-2020 08-05-2020 --- Yes
Final decision/agency action (Agency Action) 03-09-2027 04-02-2027 --- No
In Progress
The explanation for the milestone date change is outlined in the Executive Director Determination posted on the project page. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 08-05-2020 08-05-2020 --- Yes
Final decision/agency action (Agency Action) 03-09-2027 04-02-2027 --- No
In Progress
The revised schedule extends the BLMs target dates for issuance of the National Environmental Policy Act (NEPA) documents and the final order by approximately 42 days. The shift for the ROW grant shifts 60 days to accommodate internal reviews and approval. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 08-05-2020 08-05-2020 --- Yes
Final decision/agency action (Agency Action) 03-09-2027 03-09-2027 --- No
In Progress
The explanation for the milestone date change is outlined in the Executive Director Determination posted on the project page. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 08-05-2020 08-05-2020 --- Yes
Final decision/agency action (Agency Action) 03-09-2027 04-02-2027 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 08-05-2020 08-05-2020 --- Yes
Final decision/agency action (Agency Action) 03-09-2027 03-09-2027 --- No