USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Planned
BOEM is requesting these completion date modifications due to the timing of the Project Sponsor’s submission of a revised Construction and Operations Plan (COP) containing additional data and assessments that BOEM requires prior to issuing a Notice of Intent (NOI) to prepare an Environmental Impact Statement (EIS) under NEPA. BOEM has requested that the revised COP contain certain survey data for one of the proposed cable routes as well as the following assessments: the Navigational Safety Risk Assessment; Historic Resources Visual Effects Assessment for certain facilities; Marine Archaeological Resource Assessment for a particular cable route; and the Terrestrial Archeological Resource Assessment for all routes and facilities in the onshore project design envelope. The Project Sponsor intends to submit the revised COP containing all the requested information on October 27, 2025.  NMFS milestones have been adjusted to align with the new NEPA schedule.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 06-26-2025 03-27-2026 --- No
NOAA Determines ITA Application is Complete (Applicant Action) 01-26-2026 10-27-2026 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 02-27-2026 11-30-2026 --- No
Publish Proposed ITA in Federal Register (Agency Action) 10-20-2026 07-21-2027 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 09-10-2027 06-12-2028 --- No
ITA decision rendered (Agency Action) 10-12-2027 07-12-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 06-26-2025 06-26-2025 --- No
NOAA Determines ITA Application is Complete (Applicant Action) 01-26-2026 01-26-2026 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 02-27-2026 02-27-2026 --- No
Publish Proposed ITA in Federal Register (Agency Action) 10-20-2026 10-20-2026 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 09-10-2027 09-10-2027 --- No
ITA decision rendered (Agency Action) 10-12-2027 10-12-2027 --- No