USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Cancelled
The EFH milestones are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 417 days results in a commensurate shift to the EFH action milestones.  Therefore, an extension of the EFH milestones is requested based upon the extension of BOEM’s COP and EIS milestones. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 05-26-2026 02-24-2027 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 10-20-2026 07-21-2027 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-18-2027 10-19-2027 --- No
Planned
BOEM is requesting these completion date modifications due to the timing of the Project Sponsor’s submission of a revised Construction and Operations Plan (COP) containing additional data and assessments that BOEM requires prior to issuing a Notice of Intent (NOI) to prepare an Environmental Impact Statement (EIS) under NEPA. BOEM has requested that the revised COP contain certain survey data for one of the proposed cable routes as well as the following assessments: the Navigational Safety Risk Assessment; Historic Resources Visual Effects Assessment for certain facilities; Marine Archaeological Resource Assessment for a particular cable route; and the Terrestrial Archeological Resource Assessment for all routes and facilities in the onshore project design envelope. The Project Sponsor intends to submit the revised COP containing all the requested information on October 27, 2025.  NMFS milestones have been adjusted to align with the new NEPA schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 05-26-2026 02-24-2027 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 10-20-2026 07-21-2027 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-18-2027 10-19-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 05-26-2026 05-26-2026 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 10-20-2026 10-20-2026 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-18-2027 01-18-2027 --- No